Eight phases. Each one ends when something is signed.

Not when the calendar says so. A gate that has not closed is the cheapest problem you will ever have.

00

One call, no fee

Enquiry and scoping

We establish what you are making, for whom, at what price, and by when. Half of these conversations end with us telling you the project does not need us yet, or does not need us at all. That is a useful outcome.

GateScope and fee agreed in writing before any work begins.

From you

  • What you intend to make, and why
  • Target price and target launch date
  • Any existing designs, samples or suppliers

From us

  • An honest read on feasibility
  • A scope, a fee and a calendar
  • The name of the phase we would actually start at

01

2–3 weeks

Positioning

The category is mapped, the position is fixed, and the price architecture is set. Everything after this is built to constraints agreed here, which is why we do not skip it even when a client arrives with designs already drawn.

GatePositioning signed off. It becomes the brief for every later decision.

From you

  • Access to founders for two working sessions
  • Any customer or sales data you hold
  • Commercial targets

From us

  • Category and competitor map
  • Positioning statement and price architecture
  • Verbal identity and naming convention
  • Brand book

02

2 weeks

Range architecture

How many styles, in what fabrics and weights, at what margin, delivered in what sequence. A line plan is a commercial document before it is a creative one.

GateLine plan approved. Option count frozen before specification starts.

From you

  • Sign-off on option count and margin targets
  • Launch date and any drop calendar

From us

  • Range architecture and line plan
  • Option and colourway count per style
  • Target cost and target margin per line
  • Delivery sequence
Pattern book from Germany, 1760, showing bands of ink-drawn weaving drafts across a gridded page.
Pl. VPattern book, Germany, 1760. Bands of draft, worked out before a single thread was warped.

03

2–3 weeks per capsule

Specification

Technical packages are built to a standard a factory can quote from without asking a follow-up question. Bill of materials, points of measure, graded size chart, construction, trims, labelling, care and content.

GateTech packs released only after a mutual NDA is in place.

From you

  • Designs, references or existing samples
  • Fit preference and a base size
  • Any brand-mandated trim or labelling

From us

  • Tech pack per style
  • Fabric and trim specification with costed alternatives
  • Colour standards for lab dipping
  • Graded size chart

04

2–4 weeks

Supplier matching and quotation

We shortlist manufacturers whose machinery, minimums, calendar and compliance standing fit the specification, run a structured RFQ so quotations compare line by line, and review each candidate's audit position before a sample is commissioned.

GateFactory selected and terms agreed before sampling is paid for.

From you

  • Decision on market and on target landed cost
  • Sample fee and courier account, or our pass-through

From us

  • Vetted shortlist with capability notes
  • Like-for-like costing comparison
  • Factory vetting file and audit review
  • Recommendation, with the reasoning stated

05

4–8 weeks

Sampling

Proto, fit, salesman's sample, pre-production. Each round is a written comment sheet against the specification, not a conversation about impressions. The pre-production sample is approved before bulk fabric is cut.

GateNo bulk cutting without a signed pre-production sample.

From you

  • Fit session attendance, or a fit model
  • Written approval at each round

From us

  • Comment sheets against spec at every round
  • Lab dip and strike-off approvals
  • Fit correction and pattern notes
  • Approved pre-production sample
Interior of a cotton textile mill photographed in 1911, sunlight falling across rows of spinning frames on a tiled floor.
Pl. ICotton mill interior, Central Asia, 1911. Three-colour photograph by Sergei Prokudin-Gorskii.

06

30–90 days by market

Production

Purchase order issued, critical path held, long-lead components chased early. Inline inspection during the run and a final inspection at full carton availability, both to AQL sampling under ISO 2859-1.

GateShipment released against a passed final inspection.

From you

  • Deposit per agreed payment terms
  • Destination, Incoterm and delivery window

From us

  • Purchase order and time-and-action calendar
  • Weekly status against the critical path
  • Inline and final inspection reports
  • Shipment sample

07

Per Incoterm

Delivery and handover

Freight booked, documents issued, goods handed over at the agreed Incoterm. Then the supplier relationship is transferred to you, in full, with the vetting file and the correspondence. We are not a gatekeeper between a brand and its factory.

GateRelationship transferred. You own the supplier, not us.

From you

  • Balance per agreed payment terms
  • Customs broker, or our nomination

From us

  • Commercial invoice, packing list, bill of lading, certificate of origin
  • Complete factory file and contact handover
  • Defect analysis and corrective actions for the next run

Where projects actually fail

Four failures, and where in the process we catch them.

None of these are unusual. All of them are cheaper to find in phase three than in phase six.

The target price was never achievable at that minimum
Caught at 04, when quotations come back and the costing is laid out line by line. If it was already obvious at 02, we say so at 02.
The fabric behaves differently in bulk than in the swatch
Caught at 05, in the pre-production sample, which is why nothing is cut before it is signed. Bulk fabric is inspected on arrival at the factory, not on despatch from the mill.
The factory quoted a calendar it cannot hold
Caught at 06 by a time-and-action calendar with weekly checkpoints, and by chasing long-lead trims before they are the reason the season is late.
The garment passes inspection and still fits badly
Caught at 05 by fit sessions against a graded size chart rather than a single base size, and by measuring the pre-production sample at every point of measure.

Enquiries

Where would your project start?

Rarely at phase zero and rarely at phase one. Send us what exists and we will tell you which phase you are actually in.